APPLICATION INSTRUCTIONS
1- Application should be made immediately following the final finishing operations as soon as
the surface “sheen” of moisture has disappeared and slab can support the weight of an applicator.
In case of delay, thoroughly dampen the surface with clean water then applying ABA CURE.
2- Ensure that there is no free water on the surface before applying.
3- In case of hot weather and Mat concreting, the required thickness is achieved by applying 2 layers. Leave the first layer for 30-60 minutes before applying the second layer;
4- ABA CURE could be mixed with clean water (mixing ratio: ABA CURE:Water = 1:0.3-0.5 /wt) in temperate weathers;
5- Apply by spray, brush, long nap roller, or lamb's wool applicator. For best results, we recommend a low-pressure garden-type sprayer with neoprene hoses. Apply uniformly to form a continuous film.
6- Apply ABA CURE at a rate of 150-200 grams per 1.0 m2.
7- Avoid any ponding on the concrete surface.
Note:
-Prior to drying; equipment can be cleaned with soap and water.
-After applying, Protects surfaces from freezing.